SCHEDULING AND ALLOCATION OF LABOR FOR THE PROJECT OF STAGE 1 CONSTRUCTION OF MUHAMMADIYAH HOSPITAL GRESIK
DOI:
https://doi.org/10.26740/rekats.v14n01.p79-84Keywords:
Project scheduling, labor allocation, resource levelling, PDM, Microsoft Project.Abstract
This study aims to analyze the scheduling and labor allocation of the Stage 1 Construction Project of Muhammadiyah Hospital Gresik. In its execution, the project encountered an imbalance in workforce distribution, affecting time efficiency and increasing the risk of delays. The methods used include the Precedence Diagram Method (PDM) for scheduling and resource levelling to balance labor allocation. Data analysis was carried out using Microsoft Project and Microsoft Excel. The results showed that prior to resource levelling, the project duration reached 475 calendar days with daily labor fluctuations ranging from 5 to 86 workers. After applying resource levelling, the project duration was reduced to 370 calendar days with a more balanced workforce distribution of 7 to 46 workers per day. The implementation of these methods proved effective in improving labor efficiency and supporting the smooth execution of the overall project.
Downloads
References
Agustiar, I., & Handrianto, R. (2018). Evaluasi Penjadwalan Proyek Menggunakan Metode CPM Dan Kurva S. Wahana Teknik, 7(2), 99–105.
Astari, N. M., Subagyo, A. M., & Kusnadi. (2021). Perencanaan Manajemen Proyek dengan Metode CPM (Critical Path Method) dan PERT (Program Evaluation and Review Technique). Konstruksia, 13(1), 164–180.
Kristiana, R., Syafi’ur, A., Muhammad, R., Sediyanto, Y., Lawa, K., Sutikno, B., Tyas, A. H., Tatan, W., Aep, S., & Afriansyah, S. (2022). Manajemen Resiko. CV. Mega Press Nusantara. www.megapress.co.id
Listiani, T., & Kamandang, Z. R. (2023). Analisis Kebutuhan Tenaga Kerja Menggunakan Metode Resource Leveling pada Pekerjaan Struktur Bawah Gedung Bertingkat. RADIAL: Jurnal Peradaban Sains, Rekayasa Dan Teknologi, 11(1), 239–247.
Nangka, C. I. G., Sibi, M., & Mangare, J. (2018). Perataan Tenaga Kerja Pada Proyek Bangunan Dengan Menggunakan Microsoft Project (Studi Kasus: Proyek Pembangunan Terminal Akap Tangkoko Bitung). Jurnal Sipil Statik, 6(11), 867–874.
Octavi, D. M., Wahyudi, A., & Utami, C. (2019). Analisis Resource Leveling Menggunakan Network Planning pada Pembangunan Rusunawa Institut Teknologi Padang. Progress in Civil Engineering Journal, 1(2).
Pratama, M. R. D. (2021). Analisis Penerapan Rantai Pasok Terhadap Manajemen Pembiayaan Proyek Kontruksi Bangunan Gedung X Di Jakarta. Lakar: Jurnal Arsitektur, 4(1), 34–39.
Priyo, M., & Aulia, M. R. (2015). Aplikasi metode time cost trade off pada proyek konstruksi: studi kasus proyek pembangunan Gedung Indonesia. Semesta Teknika, 18(1), 30–43.
Sholeh, M. N., Suwarto, F., Dharmo, B., & Hartono. (2021). Pelatihan Pengenalan Microsoft Project 2019 pada Kontraktor dan Konsultan Bersama Himpunan Pengembangan Jalan Indonesia (HPJI) Jawa Tengah. Jurnal Pasopati, 3(2).
Waney, E. V. Y., & Ruitan, S. M. (2022). Perencanaan Waktu dan Penjadwalan Pelaksanaan Proyek Pembangunan Rusun TNI di Minahasa Utara. Prosiding Seminar Nasional Produk Terapan Unggulan Vokasi, 1(1), 290–295.
Abstract views: 1
,
PDF Downloads: 0